NEW QUESTION # 110
If the run time per piece on operation B is shorter than that on A, the first batch must be larger enough to avoid idle time on operation A

  • A. False
  • B. True

Answer: A


NEW QUESTION # 111
Which of the following results in inventory build ups in low-demand periods?

  • A. Hybrid strategy
  • B. None of these
  • C. Chase strategy
  • D. Production leveling strategy

Answer: D


NEW QUESTION # 112
A control chart for averages and ranges tracks which critical characteristics of a frequency distribution?

  • A. shape and spread
  • B. control and tolerance
  • C. center and spread
  • D. specification limit and center

Answer: C


NEW QUESTION # 113
A system that forecasts when the various demands will be made by the system on central supply is known as:

  • A. Conjecture supply planning
  • B. Anticipated centralized system
  • C. Distribution requirements planning
  • D. Predictive central system

Answer: C


NEW QUESTION # 114
A tracking signal can be used to monitor the quality of forecast.

  • A. True
  • B. False

Answer: A


NEW QUESTION # 115
Which of eth following is NOT the source of waste in the design of the manufacturing system?

  • A. Movement
  • B. Environment
  • C. Process
  • D. Methods

Answer: B


NEW QUESTION # 116
are determined by the computer's material requirement plan logic based upon the gross requirements for a particular part.

  • A. None of the above
  • B. Planned orders
  • C. Operational plan
  • D. Open order file

Answer: B


NEW QUESTION # 117
Any changes can be made to the MPS as long as it is within the limits set by the production plan. Changes are routine and are often made by the computer program. This is the scenario in zone of time fence.

  • A. Slushy Zone
  • B. None of these
  • C. Liquid Zone
  • D. Frozen Zone

Answer: C


NEW QUESTION # 118
Which of the following is NOT categorized modeling approaches in SCM?

  • A. Supply Chain Network Design Method:
  • B. MIP Optimization Modeling:
  • C. Heuristic Methods:
  • D. None of these

Answer: D


NEW QUESTION # 119
Total the forecast demand for the planning horizon.
Determine the opening inventory and the desired ending inventory
Calculate the total production required as follows:
Total Production = total forecast + back orders
+ ending inventory - opening inventory
Calculate the production required each period by dividing the total production by the number of periods.
Calculate the ending inventory for each period.
Above is the general procedure

  • A. To identify the production gaps
  • B. All of these
  • C. for developing a level production
  • D. to forecast capacity requirements to meet demand

Answer: C


NEW QUESTION # 120
What occurs when the cost of ordering equals the cost of carrying?

  • A. Ordering cost quantity
  • B. Exact-order completeness
  • C. Economic-order quantity
  • D. Predetermined carrying cost

Answer: C


NEW QUESTION # 121
The formula to calculate the period-order quantity is:

  • A. Period-order quantity = EOQ * average monthly usage
  • B. Period-order quantity = EOQ / average monthly usage
  • C. Period-order quantity = EOQ / average weekly usage Where EOQ is Economic-Order- Quantity
  • D. Period-order quantity = EOQ / average yearly usage

Answer: C


NEW QUESTION # 122
Material Requirements Planning (MRP) is:

  • A. A schedule establish for the production agenda
  • B. The system used to provide available inventory
  • C. All of the above
  • D. The system used to avoid missing parts.

Answer: D


NEW QUESTION # 123
When a quantity of an item equal to the order point quantity is set aside and not touched until all the main stock is used up, this strategy is called:

  • A. Wait-for-next strategy
  • B. Dual system
  • C. Two-fold system
  • D. Two-bin system

Answer: D


NEW QUESTION # 124
Process specifications are step-by-step set of instructions describing how the product is made this information is usually recorded an:

  • A. A Routing file
  • B. Both A& B are the same
  • C. A route sheet
  • D. Process sheet

Answer: B


NEW QUESTION # 125
If the volume of manufactured components can be increased, then the unit cost of the components, and the final product, will be reduced.

  • A. True
  • B. False

Answer: A